ATP Checking when creating delivery note?
题目
ATP Checking when creating delivery note?
Dear:I have define the atp checking rule B for delivery and allow sap to take the released production order into ATP checking scope.But why sap will still say there is no availiable stock if I create delivery note before the goods receipt of the released production order?Thanks alot
答案
Thank you for your attention ATP checking rule A(SD order) and B(SD delivery) will take released production order into checking scope.and I have activated the ATP checking for delivery item.查看原帖>>
举一反三
已知函数f(x)=x,g(x)=alnx,a∈R.若曲线y=f(x)与曲线y=g(x)相交,且在交点处有相同的切线,求a的值和该切线方程.
我想写一篇关于奥巴马的演讲的文章,写哪一篇好呢?为什么好
最新试题
- 一个重50牛的物体放在水平桌面上时,物体对桌面的压力大小等于多少牛,方向?物体放在斜面上静止时,物体对斜面的压力大小大于,等于,还是小于50牛?
- 向碳酸钠、碳酸氢钠 分别加入石灰水 现象?
- 已知函数f(x)=ln(ax+1)+2/(x+1),其中a>0 ①讨论函数f(x)在(0,+∞)的单调性.②若
- 高一数学题``````````yaya`````````come on!
- 用一架天平分别称出1克~31克不同物体的重量,至少要准备()个天平的砝码,每个砝码的重量是多少?
- 已知向量AB=(4,2),向量BC=(x,y)向量CD=(3,5),当向量BC∥DA求实数x,y对应满足的关系式
- 在一个周长是80厘米的正方形木板上,锯下一个最大的圆,这个圆的面积是多少平方厘米?
- (√8/27-√3)√6
- No matter how hard the problem may be ,I will try my best to _______ it
- 9点到10点之间,什么时候时针和分针成一条直线
热门考点